27/03/2026
Project update from one of our latest large-scale laboratory fit-out projects for an industrial processing client.
This high-spec facility will house multiple laboratories and needs some really TECHY kit to support the client’s needs. Each lab requires specialist coordination across services, infrastructure and equipment.
The building has now been fully stripped out, with multiple trades on site working under the direction of our contracts team.
A recent site meeting ensured all specialist contractors are aligned with the technical requirements, including:
• Bespoke HVAC system – working closely with the client to calculate precise environmental requirements
• Fume extraction – installation of 7 industrial fume cupboards to support safe laboratory operations
• Specialist Gases – including Nitrogen, Argon, Helium and Carbon Monoxide
• Electrical infrastructure – designed to support 6 new laboratories and associated equipment
We’re also installing high-performance TopLab Plus Align worktops to meet the durability and chemical resistance demands of the environment.
Looking forward to sharing the completed facility soon.