14/02/2026
FEBRUARY 11, 2026/WEDNESDAY
Control No. NORPI-D2MOM-2026
Notice of Reschedule of Power Interruption (NORPI) along 5LI2BLO-MRW 69kV line on February 15, 2026.
Please be informed that the power interruption of the 5LI2BLO-MRW 69kV line, as requested, has been rescheduled. The details of the shutdown are provided below:
Date: February 15, 2026 (Sunday)
Time: 7:00 AM– 8:00 / 5:00 PM - 6:00 PM
Line Affected:
5LI2BLO-MRW 69kV Line
(Baloi-Marawi 69kV Line)
Reason/s of Activities:
1. Requested shutdown to facilitate maintenance of its DANSALAN SS.
2. NGCP MD2 TL vegetation clearing.
3. Temporary transfer of loads from Marawi Substation to Baloi Substation during RAMADAN period.
Our Baloi and Marawi Substation Engineers on duty will closely coordinate with your office during this activity.
Power will be restored ahead of schedule if all work is completed, regardless of the above-mentioned timeline. Please ensure that the necessary safety precautions are observed on your end.
Thank you for your kind understanding and usual cooperation.
OnDuty