East Slope Earthworks LLC

East Slope Earthworks LLC Excavation-Civil-Marine-Environmental business located in Cle Elum Wa, servicing all of Washington

The Cottage Lake Creek Weir Removal and Stream Restoration Project involved the complete removal of an old concrete weir...
10/12/2025

The Cottage Lake Creek Weir Removal and Stream Restoration Project involved the complete removal of an old concrete weir and the restoration of the creek to a more natural and functional state. The work began with clearing and grubbing of the site, followed by a full creek diversion to safely isolate the work area. Approximately 350 cubic yards of native material were excavated and exported to reshape the channel and reestablish a natural stream profile. Managing the large-diameter diversion pipe running through the middle of the site added an additional layer of difficulty, especially with unpredictable and uncontrolled flow fluctuations throughout construction.
To rebuild the stream-bed and enhance aquatic habitat, a total of 330 tons of imported stream-bed gravels and cobbles were placed throughout the newly shaped channel. The restoration also included the purchase and installation of twenty-nine pieces of large woody debris, each carefully positioned to promote habitat complexity and channel stability. These were secured with a total of fifty-three Manta Ray earth anchors, providing long-term strength and resilience under varying flow conditions. In addition to the in-stream work, East Slope Earthworks constructed a gravel walking path, built wood stairs providing access down to the creek, and installed one hundred twenty-five feet of split rail cedar fencing to improve the site’s functionality and appearance.
Despite the project’s technical challenges, the work was completed safely, efficiently, and to the owner’s satisfaction. The collaboration with the project owner was excellent, and East Slope Earthworks looks forward to future opportunities to work together on similar restoration efforts.

Marblemount Fish Hatchery Waterline Replacement: Work performed under this contract included the removal and replacement...
10/10/2025

Marblemount Fish Hatchery Waterline Replacement: Work performed under this contract included the removal and replacement of existing 36-inch and 24-inch steel rearing pond supply lines with new HDPE pipe of the same diameters. A total of 700 linear feet of 36-inch HDPE pipe and 800 linear feet of 24-inch HDPE pipe were installed, replacing aging steel infrastructure that served critical fish-rearing facilities.
The scope of work also included cultural resources monitoring, ensuring that all excavation and ground disturbance were conducted in compliance with environmental and historical preservation standards. Additional project elements included the removal and replacement of 396 linear feet of chain-link fencing, repaving of disturbed areas, and importing select backfill material while disposing of unsuitable native soils on site.
One of the project’s defining challenges was the August 1st deadline for completing and commissioning the 36-inch HDPE line, which was essential to maintain continuous water supply for fish operations. The crew met this deadline through exceptional coordination and efficiency. Working with large-diameter HDPE pipe presented unique technical challenges—particularly its tendency to expand and contract with temperature changes. The team also managed water seepage from the rearing ponds and addressed several unforeseen field changes with practical, field-based solutions.
Despite these complexities, the project was completed safely, on time, and to specification. The crew’s performance, adaptability, and commitment to quality were outstanding. Working with the owner was a pleasure—they were professional, cooperative, and engaged throughout the process. We look forward to collaborating on future projects together.

We are a continuously growing company with a full schedule ahead of us and are looking to add a skilled, motivated forem...
07/16/2025

We are a continuously growing company with a full schedule ahead of us and are looking to add a skilled, motivated foreman or superintendent to our team. If you or anyone you know is looking for a change or a new start, please reach out.

This project involved replacing aging storm infrastructure and improving drainage across several locations on Bainbridge...
06/25/2025

This project involved replacing aging storm infrastructure and improving drainage across several locations on Bainbridge Island, including NE Murden Cove Drive, Manitou Beach Drive NE, Weaver Road NW, and Irene Place NE. Crews installed new storm pipe and structures and replaced deteriorating cross culverts at Silven Avenue NW, NE Torvanger Road, and—under an additive alternate—Meadowmeer Circle NE and Misty Vale Place NE.

Work was performed under tight site constraints and heavy traffic conditions, requiring precise coordination, careful staging, and traffic control measures. Despite the challenges, our crews maintained good attitudes, and a strong focus on safety while working long hours to meet project demands. Full roadway restoration followed each phase, including excavation, backfill, stormwater treatment elements, and new pavement.

Our team did a great job completing this tough project, delivering high-quality results, all while maintaining excellent communication with the City and surrounding community throughout the process. Great job guys.

This project involved replacing a failing rock retaining wall with a 60-foot-long drilled shaft soldier pile wall with w...
03/28/2025

This project involved replacing a failing rock retaining wall with a 60-foot-long drilled shaft soldier pile wall with wood lagging. We installed five W12x40 piles and three W14x68 piles, with all holes drilled using a TD25 TC Techno Drill and a 24-inch auger.
The project presented significant challenges due to the tight site conditions and proximity to an electrical vault. Despite these constraints, all work was completed in-house. The original wall was carefully and systematically removed as the new wall was constructed, minimizing the risk of sloughing.
Once the structural elements were in place, the wall was backfilled and compacted to ensure long-term stability. Drainage features were incorporated to prevent water buildup behind the wall, reducing future maintenance needs. The finished structure not only enhances the site's stability but also improves its overall functionality and appearance. Once again hats off to the crew for adding another great project to our resume.

Looking for a truck driver. Based in Cle Elum, mostly prevailing wage projects, medical, dental, retirement. Please mess...
02/13/2025

Looking for a truck driver. Based in Cle Elum, mostly prevailing wage projects, medical, dental, retirement. Please message or call me if interested.

Dustin (509)899-7056

We had the opportunity to be part of an incredible project this summer in Neah Bay, WA, alongside our friends at Duwamis...
02/03/2025

We had the opportunity to be part of an incredible project this summer in Neah Bay, WA, alongside our friends at Duwamish Services. This opportunity arose thanks to our extensive experience in the marine industry, with over 40 years of combined expertise in the marine industry.

Our role in this project was to provide essential equipment and, most importantly, experienced labor for underwater demolition and cleanup. The work involved collaborating with the dive crew to remove nine derrick vessels—some still floating and others submerged on the seafloor. The sunken vessels were carefully extracted using a clam bucket and rigging individual components. All debris was then loaded onto a flat deck barge and transported to Seattle for upland disposal.

It was an honor to contribute to such a meaningful project, and we take great pride in the work the team accomplished.

This project, located in Puyallup, WA, involved the removal of hazardous rock walls, grading, and the importation of fil...
01/03/2025

This project, located in Puyallup, WA, involved the removal of hazardous rock walls, grading, and the importation of fill to create safe, even slopes. Hydro seeding was applied to complete the area, providing a secure space for children to play and observe the field. Additionally, the project included installing fencing around an electrical transformer and repairing existing fencing around portable classrooms, enhancing both safety and functionality.

This project, located in Winthrop, WA, involved the installation of precast concrete boat ramp planks and the constructi...
01/03/2025

This project, located in Winthrop, WA, involved the installation of precast concrete boat ramp planks and the construction of a new crushed rock access trail with cast-in-place curbing. The gravel parking area was scarified and upgraded with 300 tons of crushed rock, which was carefully placed, graded, and rolled to ensure durability and functionality. Additionally, a 2-inch irrigation line was installed through the parking area to enhance site infrastructure. Designed to provide safe and convenient river access, the project serves river rafts, tubes, and swimmers, enhancing recreational opportunities in the area.

12/27/2024

We are looking for office help 1-2 days a week. Having payroll experience would be preferred. Tasks include, payroll, AP, mail, and misc other items. Please reach out if interested or if you know someone interested.

Pay will be based on experience.

Dustin (509)899-7056

Another great job completed by our crews.
12/20/2024

Another great job completed by our crews.

The Ridgecrest Elementary safety project is almost complete! 🏫 Improvements include removing hazardous rock walls, regrading pathways, repairing fencing, and adding safety measures around the campus.

These upgrades ensure safer outdoor spaces for students to learn and play. Thank you for supporting the 2024 Capital Levy helping us create secure environments for our schools!

Read the full story on our website at https://bit.ly/4flRkO8

Address

Cle Elum, WA

Alerts

Be the first to know and let us send you an email when East Slope Earthworks LLC posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Practice

Send a message to East Slope Earthworks LLC:

Share

Share on Facebook Share on Twitter Share on LinkedIn
Share on Pinterest Share on Reddit Share via Email
Share on WhatsApp Share on Instagram Share on Telegram